Here you can find the list of the requirements identified for the COGITO Construction Process ontology and their main features.
Identifier | Competency Question / Fact |
---|---|
PROC-1 | A project is related to one or more processes |
PROC-2 | A process can reflect the as-planned original process, the as-planned enriched process and the as-is process |
PROC-3 | A project includes data about its identifier, name, author, creation date, planned start and end dates, actual start and end dates, time step and time window |
PROC-4 | A process has a cost, which is measured in a certain currency |
PROC-5 | A task has a cost, which is measured in a certain currency |
PROC-6 | A task belongs to a certain process |
PROC-7 | A task can add, remove, control or repair elements |
PROC-8 | A task includes result, progress and priority information |
PROC-9 | A task can have a date of creation, of planned and actual beginnings, and of planned and actual ends |
PROC-10 | A task can have sub-tasks |